Kallista Sewerage Project
Yarra Valley Water is in the planning stage of this project to provide sewerage services to properties in Kallista, The Patch and Menzies Creek.
As part of Yarra Valley Water’s Community Sewerage Program, the Kallista Sewerage Project will provide a new sewerage service to properties in Kallista, The Patch and Menzies Creek that can’t contain their own wastewater on-site.
Providing a new sewerage service to the area will eventually involve constructing new sewer pipes in local streets, and then having properties connect to those newly constructed pipes.
PROJECT UPDATE - STAGE 1
July 2019
Project updates care of yvw.com.au
Construction on the lower section of the Olinda-Menzies Creek transfer pipeline commenced in February 2019 and is on schedule to be completed by November 2019.
This infrastructure will form the back bone of the network and enable the ultimate completion of Kallista Sewerage Project Stage 1 and 2 which will service over 1000 properties in Kallista, The Patch, Menzies Creek and Sherbrooke.
Properties in Package 1 and Package 3 investigation areas (as shown on the above map) are scheduled to be declared ready for connection by mid 2020. Construction commenced on Package 1 in February 2019 and construction on Package 3 is due to commence late in 2019.
(yvw.com.au)
(yvw.com.au)
Package stages listed as: